Wednesday, July 10, 2013

A can lay railway track between two given stations in 16 days and B can... - with answer

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in _____ days.












Answer:

9 3 days
5